NA 022

DKE German Commission for Electrical, Electronic & Information Technologies of DIN and VDE

Project

Control and protection systems for high-voltage direct current (HVDC) power transmission systems - Off-site real-time simulation testing

Abstract

This document provides guidance on off-site real-time simulation tests of control and protection (C&P) systems for HVDC power transmission systems. The off-site real-time simulation tests are carried out after the testing of C&P devices and prior to on-site system tests. This document covers point-to-point, back-to-back, and multi-terminal HVDC systems of line commutated converters (LCC), voltage-sourced converters (VSC) and hybrid HVDC technologies. In order to provide practical guidance for the functional performance tests of HVDC power transmission systems, this document covers the test environment, the contents and methods of functional performance tests, and the test report.

Begin

2024-11-15

Planned document number

DIN IEC/TR 63368

Project number

02232696

Responsible national committee

DKE/K 331 - Leistungselektronik  

Contact

Peter Täubl

Merianstr. 28
63069 Offenbach am Main

Tel.: +49 69 6308-281

Send message to contact